Activity |
Type |
Generic Milestone to Issue Final Safety Evaluation1 |
Design Certifications and Standard Design Approvals (including Topical Reports 2 required to support the application and submitted in parallel or earlier than the application) |
Light Water Power Reactor (LWR) – Part 52 |
42 months |
Non-LWR – Part 52 |
36 months |
Licenses
(including Topical Reports2 required to support the application and submitted in parallel or earlier than the application)
|
Uranium Recovery – Part 40 |
36 months |
Fuel Cycle Facilities – Parts 40 and 70 |
36 months |
Operating (LWR) – Part 50 |
42 months |
Operating (Non-power production or utilization facility (NPUF) or Non-LWR) – Part 50 |
36 months |
Combined 3 (LWR or non-LWR referencing a certified design) – Part 52 |
30 months |
Combined3 (LWR not referencing a certified design) – Part 52 |
42 months |
Combined3 (non-LWR not referencing a certified design) – Part 52 |
36 months |
Manufacturing (LWR or non-LWR referencing a certified design) – Part 52 |
30 months |
Manufacturing (non-LWR not referencing a certified design) – Part 52 |
36 months |
Manufacturing (LWR not referencing a certified design) – Part 52 |
42 months |
Permits and Authorizations |
Construction Permit – Part 50 |
36 months |
Limited Work Authorization – Parts 50 and 52 |
36 months |
Early Site Permit – Part 52 |
24 months |
License Amendments
(including power uprates) |
Decommissioning – Parts 30, 40, 50 and 70 |
24 months |
Uranium Recovery – Part 40 |
12 months |
Fuel Cycle Facilities – Parts 40 and 70 |
24 months |
Construction Permit – Part 50 |
24 months |
Operating (all) – Part 50 |
24 months |
Early Site Permit – Part 52 |
24 months |
Design Certification – Part 52 |
24 months |
Combined3 (under construction) – Part 52 |
9 months |
Combined3 (operating or not under construction) – Part 52 |
24 months |
License Renewals |
Uranium Recovery - Part 40 |
36 months |
Fuel Cycle Facilities – Parts 40 and 70 |
24 months |
Operating (NPUF and non-LWR) – Part 50 |
36 months |
Operating (LWR) and Combined (LWR) – Parts 50, 52, and 54 |
18 months |
Early Site Permits – Part 52 |
18 months |
Design Certification – Part 52 |
18 months |
Manufacturing - Part 52 |
18 months |
Other Activities |
|
|
Certificates of Compliance:
New, Amendment, or Renewal |
Transportation – Part 71 |
36 months |
Storage – Part 72 |
36 months |
Topical Reports2 |
Permit (LWR, non-LWR, or NPUF not supporting a permit or amendment) – Part 50 |
24 months |
Operating (LWR, non-LWR, or NPUF not supporting an initial license) – Part 50 |
24 months |
Design Certifications (LWR or non-LWR not supporting a design certification or amendment) – Part 52 |
24 months |
Combined3 (LWR or non-LWR not supporting a COL or amendment) – Part 52 |
24 months |
License Expansions
(e.g., new site)
|
Uranium Recovery – Part 40 |
36 months |
Independent Spent Fuel Storage Installation: New, Amendment, or Renewal |
Storage – Parts 50, 52 and 72 |
36 months |
Exemptions |
All Parts of 10 CFR |
24 months |
Code Reliefs |
Operating – Part 50 |
24 months |
Combined3 (under construction) – Part 52 |
9 months |
Combined3 (operating or not under construction) – Part 52 |
24 months |
License Transfers |
Permit - Part 50 |
24 months |
Operating – Part 50 |
24 months |
Manufacturing – Part 52 |
24 months |
Early Site Permit – Part 52 |
24 months |
Combined3 – Part 52 |
24 months |